Last wind turbine of Kittlitz III has been installed

The wind farm Kittlitz III in Brandenburg (Germany) consists of five wind turbines, type Vestas V126 and V136, with a total nominal capacity of 17.25 megawatts. On 01/04/2019 the construction of the foundation started, the first turbine has been installed on 20/09/2019. On 30/10/2019 the last turbine has been commissioned. The acceptance of the experts is ecpected in calender week 48. The errection and the commissioning of the substation was already completed in september. A sixth turbine is actually errected as an extension of Kittlitz II for the company Repower and is expected to be commissioned soon.